The post Data centers turn to jet engines and diesel generators as AI power needs surge appeared on BitcoinEthereumNews.com. Companies building data centers areThe post Data centers turn to jet engines and diesel generators as AI power needs surge appeared on BitcoinEthereumNews.com. Companies building data centers are

Data centers turn to jet engines and diesel generators as AI power needs surge

2025/12/27 19:25
4분 읽기
이 콘텐츠에 대한 의견이나 우려 사항이 있으시면 crypto.news@mexc.com으로 연락주시기 바랍니다

Companies building data centers are increasingly relying on jet engine-based turbines and fossil fuel generators to meet electricity demands, as bottlenecks in supply chains and lengthy grid connection processes push developers toward alternative power solutions.

Producers of turbines derived from aircraft engines and diesel-powered generators say orders have jumped as data center operators look for ways to avoid waiting for traditional grid hookups and larger gas turbines to become available.

“The incentives have never been greater for any sort of technology that can supply power,” according to Kasparas Spokas, who directs the electricity programme at the Clean Air Task Force.

The scramble for on-site electricity comes as data centers encounter waiting periods stretching to seven years for grid connections, along with public resistance over how their energy consumption affects utility costs.

Installing power equipment like jet engine turbines and generators directly at data center locations allows companies to run their artificial intelligence systems without needing immediate grid access.

Major tech players secure jet engine power

GE Vernova has agreed to provide data center operator Crusoe with turbines adapted from aircraft engines. These units are projected to generate close to 1 gigawatt of electricity for the Stargate data center in Texas, which will serve OpenAI, Oracle and SoftBank.

Ken Parks, who serves as chief financial officer at GE Vernova, informed investors in December that the firm was experiencing “growing demand” for its aircraft-derived and smaller gas units, which “serve as bridge power supporting data centre needs.”

The company’s aircraft-based turbine orders increased by one-third during the first nine months of 2025 when measured against the same period in the prior year.

ProEnergy has delivered over 1 gigawatt worth of 50-megawatt gas turbines that come directly from jet engine designs. Though the company increasingly manufactures components independently, it continues using CF6-80C2 engine cores, the same type found in Boeing 747 aircraft.

“We can deliver more quickly than bigger original equipment manufacturers,” said Andrew Gilbert, a partner at Energy Capital Partners, which holds the majority stake in ProEnergy Holdings. “The ability to find a few hundred megawatts to get started with, and then grow over time is useful too.”

Aviation startup Boom Supersonic, which counts Sam Altman among its backers, struck a deal to sell turbines to Crusoe that should deliver 1.2 gigawatts of power. These turbines are “virtually identical” to units designed for the company’s aircraft.

Boom Supersonic plans to channel profits from power turbine sales into financing its jet manufacturing operations.

“Three or four years ago I imagined we would do the airplane first and energy second,” chief executive Blake Scholl told the Financial Times. “But then I got a call from Sam Altman who said: ‘Please, please, please make us something.’”

Diesel generator demand doubles

Diesel and gas-powered generators are also seeing increased adoption. Cummins has delivered more than 39 gigawatts of power equipment to data centers and roughly doubled its production capacity this year.

Though data centers traditionally keep generators as emergency backup systems, Paulette Carter, who leads data center operations at Cummins, notes they’re witnessing “growing interest in on-site primary power.”

Energy Secretary Chris Wright has floated the idea of tapping existing backup generators to strengthen the electrical grid, telling Fox News in November: “We will take backup generators already at data centers or behind the back of a Walmart and bring those on when we need extra electricity production.”

Higher costs for on-site power solutions

On-site power costs appear higher than standard grid connections, since these arrangements lack the cost advantages that utilities gain from large-scale operations. BNP Paribas analysts calculated power prices at a behind-the-meter gas facility that Williams Company is constructing in Ohio for Meta at $175 per megawatt hour, roughly twice what industrial customers typically pay for electricity.

The power rush may ease when major technology companies reduce their infrastructure spending.

“We’re in a very strong market right now, but it won’t stay like that forever,” said Mark Axford of Axford Turbine Consultants.

Join Bybit now and claim a $50 bonus in minutes

Source: https://www.cryptopolitan.com/data-centers-jet-engines-diesel-generators/

시장 기회
플러리싱 에이아이 로고
플러리싱 에이아이 가격(SLEEPLESSAI)
$0.01766
$0.01766$0.01766
+2.37%
USD
플러리싱 에이아이 (SLEEPLESSAI) 실시간 가격 차트
면책 조항: 본 사이트에 재게시된 글들은 공개 플랫폼에서 가져온 것으로 정보 제공 목적으로만 제공됩니다. 이는 반드시 MEXC의 견해를 반영하는 것은 아닙니다. 모든 권리는 원저자에게 있습니다. 제3자의 권리를 침해하는 콘텐츠가 있다고 판단될 경우, crypto.news@mexc.com으로 연락하여 삭제 요청을 해주시기 바랍니다. MEXC는 콘텐츠의 정확성, 완전성 또는 시의적절성에 대해 어떠한 보증도 하지 않으며, 제공된 정보에 기반하여 취해진 어떠한 조치에 대해서도 책임을 지지 않습니다. 본 콘텐츠는 금융, 법률 또는 기타 전문적인 조언을 구성하지 않으며, MEXC의 추천이나 보증으로 간주되어서는 안 됩니다.