LOSSES due to “ghost” or non-existent flood control projects were estimated at P180 billion since 2016, Senator Panfilo “Ping” M. Lacson, who heads the Senate committee probing anomalous projects, claimed on Wednesday. “We are looking at 30,000 flood control projects since 2016. If we extrapolate based on earlier findings that more than 600 out of […]LOSSES due to “ghost” or non-existent flood control projects were estimated at P180 billion since 2016, Senator Panfilo “Ping” M. Lacson, who heads the Senate committee probing anomalous projects, claimed on Wednesday. “We are looking at 30,000 flood control projects since 2016. If we extrapolate based on earlier findings that more than 600 out of […]

P180B likely lost to ‘ghost’ projects since 2016, senator says

2025/12/03 21:25

LOSSES due to “ghost” or non-existent flood control projects were estimated at P180 billion since 2016, Senator Panfilo “Ping” M. Lacson, who heads the Senate committee probing anomalous projects, claimed on Wednesday.

“We are looking at 30,000 flood control projects since 2016. If we extrapolate based on earlier findings that more than 600 out of 10,000 projects were ghost, we estimated that 6% or higher of 30,000 projects could mean P180 billion or higher went to ghost projects,” he said in a statement.

He added that the estimates were based on the 10,000 flood control projects inspected so far, which found that about 600 of them were nonexistent.

“Imagine, we likely lost P180 billion to ghost projects, and we have not yet started counting our losses to substandard projects,” Mr. Lacson added.

He said that the estimates had rendered the number of projects tackled by the Senate Blue Ribbon Committee as “minuscule.”

“The Blue Ribbon Committee remains ready to help relevant agencies like the Independent Commission for Infrastructure, Department of Justice and Office of the Ombudsman in pursuing charges against those involved, if it gets new information,” Mr. Lacson said. 

The committee has been investigating kickbacks involving multibillion-peso flood control projects, following reports that lawmakers and public officials benefited from infrastructure funds allocated since 2022.

The senator added that the Senate and the House of Representatives have agreed to simplify the bicameral conference committee (bicam) that would only tackle the disagreeing provisions of the budget bill.

“This will be simpler and more transparent and that is our intention. In the bicam, we will ensure transparency, all the way to the bill being enrolled,” Mr. Lacson said.

Malacañang announced earlier that the bicameral conference committee meetings will be livestreamed, following public calls for more transparency and accountability in the budget process. 

DPWH ‘GHOST’ PROJECTS
Meanwhile, the Commission on Audit (CoA) flagged the Department of Public Works and Highways (DPWH) after some regional offices declared nearly P2 billion worth of infrastructure projects as accomplished nationwide despite the works not being completed in 2024.

State auditors gave a qualified opinion on the DPWH’s financial report due to “aggregate uncorrected misstatements” involving the agency’s billions of pesos worth of infrastructure, including P1.95 billion of projects marked as completed despite unfinished work.

“Some DPWH offices reported 100% project accomplishments in the Report on Publicized Government Programs, Projects and Activities,” CoA said in its 2024 audit report.

“However, ocular inspection and validation of the actual physical status revealed that these projects were not completed within the contract time due to defects, deficiencies requiring repairs and unfinished pay or work items,” it added.

Public Works Secretary Vivencio B. Dizon did not immediately reply to a Viber message seeking comment.

The DPWH has come under tighter scrutiny following allegations that flood control projects were tied to a multibillion‑peso kickback scheme involving politicians, officials and government contractors.

The projects, which auditors flagged as inaccurately tagged as finished, were found nationwide, with engineering offices in the Cordillera Administrative Region (CAR), Mimaropa, Western Visayas, and Northern Mindanao among those cited.

CoA also flagged that DPWH paid the “final progress billings” of 48 projects totaling P2.18 billion despite unfinished work or defects.

In CAR, the full amount of P1.3 billion was paid for 29 projects that were “not yet fully completed due to unfinished works.”

“On the other hand, it was noted in Region 3 that final payments on seven projects and the release of retention money for two projects were already made,” state auditors said, referring to 19 projects totaling P876.29 billion that faced completion delays. “The payment could be deemed ‘irregular.’”

CoA urged the DPWH to refrain from releasing project completion payments for projects not yet completed or “satisfactorily implemented.”

“Require contractors to immediately rectify or complete noted deficiencies and deliver all contractual requirements; otherwise forfeit their performance securities and consider them for blacklisting, if warranted,” state auditors said. — Adrian H. Halili and Kenneth Christiane L. Basilio

Disclaimer: The articles reposted on this site are sourced from public platforms and are provided for informational purposes only. They do not necessarily reflect the views of MEXC. All rights remain with the original authors. If you believe any content infringes on third-party rights, please contact service@support.mexc.com for removal. MEXC makes no guarantees regarding the accuracy, completeness, or timeliness of the content and is not responsible for any actions taken based on the information provided. The content does not constitute financial, legal, or other professional advice, nor should it be considered a recommendation or endorsement by MEXC.

You May Also Like

Team Launches AI Tools to Boost KYC and Mainnet Migration for Investors

Team Launches AI Tools to Boost KYC and Mainnet Migration for Investors

The post Team Launches AI Tools to Boost KYC and Mainnet Migration for Investors appeared on BitcoinEthereumNews.com. The Pi Network team has announced the implementation of upgrades to simplify verification and increase the pace of its Mainnet migration. This comes before the token unlock happening this December. Pi Network Integrates AI Tools to Boost KYC Process In a recent blog post, the Pi team said it has improved its KYC process with the same AI technology as Fast Track KYC. This will cut the number of applications waiting for human review by 50%. As a result, more Pioneers will be able to reach Mainnet eligibility sooner. Fast Track KYC was first introduced in September to help new and non-users set up a Mainnet wallet. This was in an effort to reduce the long wait times caused by the previous rule. The old rule required completing 30 mining sessions before qualifying for verification. Fast Track cannot enable migration on its own. However, it is now fully part of the Standard KYC process which allows access to Mainnet. This comes at a time when the network is set for another unlock in December. About 190 million tokens will unlock worth approximately $43 million at current estimates.  These updates will help more Pioneers finish their migration faster especially when there are fewer validators available. This integration allows Pi’s validation resources to serve as a platform utility. In the future, applications that need identity verification or human-verified participation can use this system. Team Releases Validator Rewards Update The Pi Network team provided an update about validator rewards. They expect to distribute the first rewards by the end of Q1 2026. This delay happened because they needed to analyze a large amount of data collected since 2021. Currently, 17.5 million users have completed the KYC process, and 15.7 million users have moved to the Mainnet. However, there are around 3 million users…
Share
BitcoinEthereumNews2025/12/06 16:08
Solana Nears $124 Support Amid Cautious Sentiment and Liquidity Reset Potential

Solana Nears $124 Support Amid Cautious Sentiment and Liquidity Reset Potential

The post Solana Nears $124 Support Amid Cautious Sentiment and Liquidity Reset Potential appeared on BitcoinEthereumNews.com. Solana ($SOL) is approaching a critical support level at $124, where buyers must defend to prevent further declines amid cautious market conditions. A successful hold could initiate recovery toward $138 or higher, while failure might lead to deeper corrections. Solana’s price risks dropping to $124 if current support zones weaken under selling pressure. Reclaiming key resistance around $138 may drive $SOL toward $172–$180 targets. Recent data shows liquidity resets often precede multi-week uptrends, with historical patterns suggesting potential recovery by early 2026. Solana ($SOL) support at $124 tested amid market caution: Will buyers defend or trigger deeper drops? Explore analysis, liquidity signals, and recovery paths for informed trading decisions. What Is the Current Support Level for Solana ($SOL)? Solana ($SOL) is currently testing a vital support level at $124, following a decline from the $144–$146 resistance zone. Analysts from TradingView indicate that after failing to maintain momentum above $138, the token dipped toward $131 and mid-range support near $134. This positioning underscores the importance of buyer intervention to stabilize the price and prevent further erosion. Solana ($SOL) is in a crucial stage right now, with possible price drops toward important support zones. Recent price activity signals increased downside risks, analysts caution. TradingView contributor Ali notes that Solana may find quick support at $124 after falling from the $144–$146 resistance range. The token eventually tested $131 after failing to hold over $138 and plummeting toward mid-range support near $134. Source: Ali Market indicators reveal downward momentum, with potential short-term volatility around $130–$132 before possibly easing to $126–$127. Should this threshold break, $SOL could slide to the firmer support at $124–$125, according to observations from established charting platforms. Overall sentiment remains guarded, as highlighted by experts monitoring on-chain data. Ali warns that without robust buying interest, additional selling could intensify. TradingView analyst…
Share
BitcoinEthereumNews2025/12/06 16:33